Skip to content
Case study May 6, 2026 Author: Marcin Liebchen 12 min read

EMS and PV in production plants – case studies from Poland

EMS and PV in production plants – case studies from Poland

Article in 45 seconds

  • EMS systems integrated with PV and BESS deliver 20–35% annual energy cost savings in Polish production plants, with ROI of 2–4 years.
  • The key to success is integrating three elements: PV (generation), BESS (buffer), and EMS (the “brain”).
  • The best results are achieved by plants with a high and stable load profile operating in multi-shift mode.
  • Deployments co-financed by KPO and NFOŚiGW shorten ROI to 1.5–2.5 years.
  • EAB Solutions has delivered deployments in food processing, chemicals, metallurgy and logistics.

Why are production plants increasingly investing in EMS and PV?

After the sharp increase in energy costs in 2021–2024 (a 40–70% rise for a typical industrial consumer, according to Eurostat), Polish production plants stopped treating electricity prices as a fixed cost. The market has stabilized, but the risk of further increases remains real — and this risk is driving investment decisions in EMS, PV and BESS.

Investments in energy management systems and photovoltaics have become a purely economic decision. Plants that implemented comprehensive systems before 2024 have observed ROI that was initially estimated at 6–8 years, but in reality closed in 2–3 years. Protection against price volatility turned out to be the most valuable “side effect” in practice.

Market context: According to URE data, total installed PV capacity in Poland exceeded 20 GW by the end of 2024 (all segments). The commercial and industrial segment (>1 MW) is growing dynamically. At the same time, the EMS market for industry is growing at around 25% annually, indicating accelerating adoption. Current data: ure.gov.pl

Below we present four anonymized case studies delivered by EAB Solutions, illustrating different scenarios and outcomes of EMS and PV investments in Polish industry.

Case study #1: Food plant – B23 tariff optimization and peak shaving

Site profile

IndustryFood processing (continuous production, 3 shifts)
LocationGreater Poland Voivodeship
Contracted power (before)700 kW
Annual electricity consumption3.2 GWh
Distribution tariffB23
Solutions implementedBESS 500 kWh + EMS + PV 300 kWp

Problem

The plant struggled with systematic exceedances of contracted power (6–8 events per year) and high contracted power charges resulting from a non-optimized load profile. Continuous production made it impossible to shift processes to night hours. Annual penalties amounted to PLN 65–90k.

Implementation

In the first phase, an EMS was installed with integration of the AMI meter and process sub-metering. The system collected 6 weeks of historical data and identified three recurring peak patterns: line restart after breakfast break (around 7:30), full line start after lunch break (around 13:00), and an evening peak associated with the night shift change (around 21:30).

Based on this, a BESS with 500 kWh usable capacity and 200 kW power was selected. The BESS discharges 2 minutes ahead of the forecasted peak, reducing grid draw by 150–180 kW at critical moments. A 300 kWp PV system covers 25–30% of daytime consumption.

Results after 12 months

Contracted power reduction700 → 550 kW (−21%)
Number of exceedance penalties7 → 0 (fully eliminated)
Peak shaving savingsPLN 138k/year
PV self-consumption savingsPLN 82k/year
Total savingsPLN 220k/year
Project CAPEXPLN 810k (no co-financing)
Simple payback3.7 years

Lesson learned

Without EMS, the plant would have paid another PLN 65–90k in penalties in the first year after implementation. Key insight: the EMS prediction algorithm achieved 94% peak anticipation accuracy versus the assumed 85%, thanks to the regularity of daily production cycles in food plants — an ideal environment for machine-learning-based forecasting.

If your plant has a similar profile, contact us for a free BESS + EMS analysis and quote: info@eabsolutions.com.pl

Case study #2: Packaging manufacturer – PV + BESS + EMS with KPO co-financing

Site profile

IndustryPlastic packaging manufacturing
LocationSilesian Voivodeship
Contracted power400 kW
Annual electricity consumption1.8 GWh
Distribution tariffB23
Solutions implementedPV 500 kWp + BESS 250 kWh + EMS
Co-financingKPO A2.1.1 – 55% CAPEX (SME; intensity depends on category and location)

Problem

The plant had large roof areas (production halls) almost ideally oriented to the south. The owner considered PV alone, but analysis showed that without BESS and EMS, self-consumption given the production profile would be only 40–45% of generated energy. The rest would be exported to the grid at a low buyback price.

Implementation

The project included a 500 kWp rooftop PV system, a 250 kWh BESS buffer for solar surplus, and an EMS managing prioritization: direct PV self-consumption → charge BESS from PV → discharge BESS during power peaks → export remaining surplus to the grid.

KPO application documentation included an energy audit under EN ISO 50002, a feasibility study with a 15-year techno-economic model, and a technical design. Co-financing covered 55% of eligible costs.

Results after 12 months

PV self-consumption78% (vs. 42% without BESS and EMS)
Reduction in grid energy purchases−31%
Energy cost savingsPLN 165k/year
CO2 reduction285 t CO2/year
Gross CAPEXPLN 1,150k
KPO co-financingPLN 632k
Net CAPEX (after co-financing)PLN 518k
Simple payback (after co-financing)3.1 years

Lesson learned

KPO funding turned this project from profitable to exceptionally profitable — PLN 632k of support against PLN 518k net investment. Key process insight: documentation took 8 weeks and the application assessment took 4 months. Patience in the funding process delivered a return equal to the entire net CAPEX.

Case study #3: Industrial cold store – managing flexible loads

Site profile

IndustryCold storage and refrigerated logistics
LocationMasovian Voivodeship
Contracted power1,200 kW
Annual electricity consumption5.8 GWh
Distribution tariffB23
Solutions implementedEMS integrated with the cold store BMS + BESS 500 kWh

Challenge specifics

Industrial cold stores have a unique energy profile. High thermal inertia of chambers enables flexible compressor management. Temperature changes slowly, giving EMS a 15–30 minute window for pre-cooling or temporarily switching off compressors without risking a technology temperature breach.

Implementation

The EMS was integrated with the Building Management System (BMS), providing access to temperature telemetry from 47 cold and freezer chambers. The prediction algorithm schedules pre-cooling to hours with lower energy prices (night valley or periods of high renewable supply) and deactivates some compressors during peak demand hours.

A 500 kWh BESS plays a complementary role — it covers short peaks caused by simultaneous start-up of multiple compressors (in-rush current), which cannot be fully eliminated by process control alone.

Results after 12 months

Peak power reduction−18% (from 1,200 to ~985 kW effective)
Contracted power renegotiation1,200 → 1,000 kW (−17%)
Savings from contracted powerPLN 95k/year
Savings from load managementPLN 78k/year
Total savingsPLN 173k/year
EMS + integration costPLN 320k
Simple payback1.85 years

Lesson learned

This deployment debunks the myth that investing in EMS without PV is not worth it. The cold store had no suitable roof for PV — yet achieved ROI under 2 years solely through EMS integrated with BMS. Thermal flexibility is one of the most valuable energy assets many cold-store owners simply don’t realize they have. EMS should be the first, not the last step in an energy optimization strategy.

Case study #4: Metallurgy plant – contracted power reduction and self-consumption

Site profile

IndustryFoundry and metal processing
LocationLower Silesian Voivodeship
Contracted power2,500 kW
Annual electricity consumption11 GWh
Distribution tariffB23 (supply from GPO – own MV/MV substation)
Solutions implementedEMS + PV 800 kWp + BESS 1,000 kWh with FFR mode
Co-financingNFOŚiGW programme – energy efficiency in enterprises (40% CAPEX; programme name anonymized)

Problem

The plant has a strongly impulsive load profile. Induction and arc furnaces generate short (5–30 second) power peaks up to 3,500 kW — 40% above contracted power. A standard BESS responds in 100–500 ms, too slow to catch the impulse before it is included in the 15-minute billing window.

Implementation

The deployment required a specialized BESS configuration with a dedicated Power Conditioning System (PCS) in Fast Frequency Response (FFR) mode, enabling reaction below 20 ms. Without PCS FFR, a standard containerized LFP system reacts in 100–500 ms, which would be insufficient for arc furnace impulses. The EMS monitors voltage and current on busbars at 100 Hz, providing a real-time trigger signal for PCS.

An 800 kWp PV installation on hardened areas (parking and yards) covers about 15–18% of daytime consumption in summer — relatively little against an 11 GWh profile, but still meaningful at high energy prices.

Results after 12 months

Elimination of impulsive exceedances100% (0 events vs. 80–100/year previously)
Contracted power renegotiation2,500 → 2,100 kW (−16%)
Savings from exceedance penaltiesPLN 240k/year
Savings from contracted powerPLN 185k/year
PV savingsPLN 130k/year
Total savingsPLN 555k/year
Gross CAPEXPLN 2,800k
NFOŚiGW co-financingPLN 1,120k
Simple payback (after co-financing)3.0 years

Common lessons – what works and what doesn’t?

What works What doesn’t deliver expected results
EMS as the first investment – data collection and potential identification PV alone without EMS and BESS – low self-consumption
Peak shaving with BESS + EMS prediction – elimination of exceedance penalties BESS without EMS integration – reactive, not proactive
Contracted power renegotiation after 6 months of EMS data Tariff change without full bill analysis
KPO/NFOŚiGW co-financing – ROI shortened by 30–50% Waiting for the “perfect moment” – every year without optimization is a loss
Integration with BMS/SCADA – full energy context Monitoring without optimization algorithms – data without action

What does a typical EMS + PV project look like in a plant?

Based on completed deployments, a typical project follows this schedule:

Stage Scope Duration
1. Audit and analysis Collect historical data, analyze bills, identify potential 2–3 weeks
2. Technical design Select BESS power and capacity, PV layout, EMS integration scheme 3–4 weeks
3. Co-financing application Feasibility study, KPO/NFOŚiGW documentation 6–10 weeks
4. BESS delivery and installation Transport, foundation, connection 2–3 days
5. PV installation Modules, inverters, cabling 2–4 weeks
6. EMS integration Configuration, algorithms, testing, commissioning 1–2 weeks
7. Monitoring and optimization Ongoing analytical supervision, algorithm updates Continuous

Total time from decision to full system go-live is usually 3–6 months (excluding waiting time for co-financing) or 9–14 months when delivered with KPO.

FAQ – frequently asked questions

Yes — and it is recommended as a first step. EMS integrated with meters and SCADA brings measurable benefits: identifying waste, optimizing process schedules, and eliminating exceedance penalties through better load control. The cost of EMS alone is much lower than a full project with BESS and PV, and payback is fast — as in the cold-store case (1.85-year ROI without PV).

Based on EAB Solutions experience, the profitability threshold for a full EMS + BESS system is around 200 kW contracted power and annual consumption above 500 MWh. Below that, PV with EMS can be profitable, but an energy storage system will have too long a payback without co-financing.

EAB Solutions EMS stores data in the cloud on servers located in Poland (ISO 27001-compliant data center). Access is encrypted (TLS 1.3), and the plant remains the sole owner of its data. On request, an on-premise setup without external data transmission is possible.

EAB Solutions BESS systems include a 5-year capacity warranty (min. 80% at 5 years) and a 10-year factory warranty for defects. Service includes 24/7 remote monitoring, EMS software updates and annual inspections. On-site response time: up to 24 hours on business days.

An EN ISO 50002 energy audit is required for most co-financing programmes (KPO, NFOŚiGW). Regardless of co-financing, the audit is also a key tool for selecting the optimal system configuration — it helps avoid over- or under-sizing BESS. EAB Solutions provides the energy audit as part of the free initial analysis.

See how much your production plant can save

Free energy analysis in 48h — we estimate real savings potential from EMS, PV and BESS based on your data.

Selection of the optimal co-financing path (KPO, NFOŚiGW, FEDS) and preparation of application documentation.

info@eabsolutions.com.pl | ul. Domaniewska 44, 02-672 Warsaw

See also

Want to reduce energy costs?

Contact us and order a free energy audit